Second Narrows Bridge

Critical Path Timelines

second narrows

"National Infrastructure enabled the general contractor to collect a substantial bonus for a successful early completion."

The Second Narrows Bridge Rehabilitation project is an example of our Critical Path Timeline achievements.

National Infrastructure was contracted for hydrodemolition of the bridge deck. The project came with stringent requirements for timely completion.

As a trusted provider of hydrodemolition services for the general contractor's other projects, National Infrastructure was called upon to complete the job within very tight timelines and any delays would have resulted in Penalties.

As an incentive for early completion the contractor would be awarded a $25,000 per day bonus for each 24 hour period that the deck work was completed prior to the established deadline.

In the event there was a delay, the contractor would be assessed a penalty of $100,000 per 24 hour period of delay.

On this project, Mac and Mac enabled the general contractor to collect a substantial bonus for a successful early completion.

NATIONAL INFRASTRUCTURE™

corpmap
  • 20240 102B Avenue
  • Langley, BC V1M 3G9
  • British Columbia
  • Canada

National Infrastructure

provides quality, high speed hydrodemolition services
throughout 
USA and Canada.